What a duplex costs to build in NSW
Construction alone typically costs $2,000–$3,800 per square metre, set mostly by the finish level. Two 150 m² homes at a mid-range finish cost about $720,000–$840,000 to build. Site works, fees, council and state charges, connections, landscaping and a 10–15% contingency take the same duplex to about $945,000–$1.25 million all-in, before land.
- $2,000–$3,800per m², construction only
- $720k–$840kto build 2 × 150 m², mid-range
- $945k–$1.25Mall-in before land, worked example
- 10–15%contingency to hold back
Free duplex site assessment. A fixed-price contract before you sign. NSW contractor licence 258735C.
By Keiron Moore, Director of CKS Projects, with 25+ years building on the South Coast. Updated October 2026.
Important Disclaimer:
“This article is general guidance, not an exact price guide, guaranteed returns, or a substitute for professional advice or a formal quote. Construction costs, rental yields, and capital growth examples reflect 2025 conditions and will vary with site constraints, design, materials, and market movements. Speak with a qualified financial adviser before making investment decisions. For accurate estimates and design recommendations for your site, contact CKS Projects. We’ll provide a comprehensive consultation and a formal quote tailored to your Wollongong duplex.”
Government charges are as published at the date shown and change over time.
Estimate your duplex in three clicks
Choose the size, the finish and your block. The range uses CKS Projects' guide figures and the current NSW charges for the Illawarra-Shoalhaven.
2 × 120 m² · Basic · Flat (CDC pathway assumed)
$680,000 – $950,000
All-in, before land, with a 10–15% contingency
- Construction
- $480,000 – $576,000
- Before contingency
- $620,000 – $825,000
2 × 120 m² · Basic · Moderate slope (CDC pathway assumed)
$715,000 – $1,005,000
All-in, before land, with a 10–15% contingency
- Construction
- $480,000 – $576,000
- Before contingency
- $650,000 – $875,000
2 × 120 m² · Basic · Steep slope (DA pathway assumed)
$770,000 – $1,095,000
All-in, before land, with a 10–15% contingency
- Construction
- $480,000 – $576,000
- Before contingency
- $700,000 – $955,000
2 × 120 m² · Mid-range · Flat (CDC pathway assumed)
$785,000 – $1,060,000
All-in, before land, with a 10–15% contingency
- Construction
- $576,000 – $672,000
- Before contingency
- $715,000 – $920,000
2 × 120 m² · Mid-range · Moderate slope (CDC pathway assumed)
$820,000 – $1,115,000
All-in, before land, with a 10–15% contingency
- Construction
- $576,000 – $672,000
- Before contingency
- $745,000 – $970,000
2 × 120 m² · Mid-range · Steep slope (DA pathway assumed)
$880,000 – $1,210,000
All-in, before land, with a 10–15% contingency
- Construction
- $576,000 – $672,000
- Before contingency
- $800,000 – $1,050,000
2 × 120 m² · Premium · Flat (CDC pathway assumed)
$945,000 – $1,335,000
All-in, before land, with a 10–15% contingency
- Construction
- $720,000 – $912,000
- Before contingency
- $860,000 – $1,160,000
2 × 120 m² · Premium · Moderate slope (CDC pathway assumed)
$980,000 – $1,395,000
All-in, before land, with a 10–15% contingency
- Construction
- $720,000 – $912,000
- Before contingency
- $890,000 – $1,210,000
2 × 120 m² · Premium · Steep slope (DA pathway assumed)
$1,035,000 – $1,485,000
All-in, before land, with a 10–15% contingency
- Construction
- $720,000 – $912,000
- Before contingency
- $945,000 – $1,290,000
2 × 150 m² · Basic · Flat (CDC pathway assumed)
$815,000 – $1,115,000
All-in, before land, with a 10–15% contingency
- Construction
- $600,000 – $720,000
- Before contingency
- $740,000 – $970,000
2 × 150 m² · Basic · Moderate slope (CDC pathway assumed)
$845,000 – $1,170,000
All-in, before land, with a 10–15% contingency
- Construction
- $600,000 – $720,000
- Before contingency
- $770,000 – $1,020,000
2 × 150 m² · Basic · Steep slope (DA pathway assumed)
$905,000 – $1,265,000
All-in, before land, with a 10–15% contingency
- Construction
- $600,000 – $720,000
- Before contingency
- $820,000 – $1,100,000
2 × 150 m² · Mid-range · Flat (CDC pathway assumed)
$945,000 – $1,250,000
All-in, before land, with a 10–15% contingency
- Construction
- $720,000 – $840,000
- Before contingency
- $860,000 – $1,090,000
2 × 150 m² · Mid-range · Moderate slope (CDC pathway assumed)
$980,000 – $1,310,000
All-in, before land, with a 10–15% contingency
- Construction
- $720,000 – $840,000
- Before contingency
- $890,000 – $1,140,000
2 × 150 m² · Mid-range · Steep slope (DA pathway assumed)
$1,035,000 – $1,400,000
All-in, before land, with a 10–15% contingency
- Construction
- $720,000 – $840,000
- Before contingency
- $945,000 – $1,220,000
2 × 150 m² · Premium · Flat (CDC pathway assumed)
$1,145,000 – $1,600,000
All-in, before land, with a 10–15% contingency
- Construction
- $900,000 – $1,140,000
- Before contingency
- $1,040,000 – $1,390,000
2 × 150 m² · Premium · Moderate slope (CDC pathway assumed)
$1,175,000 – $1,655,000
All-in, before land, with a 10–15% contingency
- Construction
- $900,000 – $1,140,000
- Before contingency
- $1,070,000 – $1,440,000
2 × 150 m² · Premium · Steep slope (DA pathway assumed)
$1,235,000 – $1,750,000
All-in, before land, with a 10–15% contingency
- Construction
- $900,000 – $1,140,000
- Before contingency
- $1,125,000 – $1,520,000
2 × 200 m² · Basic · Flat (CDC pathway assumed)
$1,035,000 – $1,390,000
All-in, before land, with a 10–15% contingency
- Construction
- $800,000 – $960,000
- Before contingency
- $940,000 – $1,210,000
2 × 200 m² · Basic · Moderate slope (CDC pathway assumed)
$1,065,000 – $1,450,000
All-in, before land, with a 10–15% contingency
- Construction
- $800,000 – $960,000
- Before contingency
- $970,000 – $1,260,000
2 × 200 m² · Basic · Steep slope (DA pathway assumed)
$1,125,000 – $1,540,000
All-in, before land, with a 10–15% contingency
- Construction
- $800,000 – $960,000
- Before contingency
- $1,025,000 – $1,340,000
2 × 200 m² · Mid-range · Flat (CDC pathway assumed)
$1,210,000 – $1,575,000
All-in, before land, with a 10–15% contingency
- Construction
- $960,000 – $1,120,000
- Before contingency
- $1,100,000 – $1,370,000
2 × 200 m² · Mid-range · Moderate slope (CDC pathway assumed)
$1,245,000 – $1,630,000
All-in, before land, with a 10–15% contingency
- Construction
- $960,000 – $1,120,000
- Before contingency
- $1,130,000 – $1,420,000
2 × 200 m² · Mid-range · Steep slope (DA pathway assumed)
$1,300,000 – $1,725,000
All-in, before land, with a 10–15% contingency
- Construction
- $960,000 – $1,120,000
- Before contingency
- $1,185,000 – $1,500,000
2 × 200 m² · Premium · Flat (CDC pathway assumed)
$1,475,000 – $2,035,000
All-in, before land, with a 10–15% contingency
- Construction
- $1,200,000 – $1,520,000
- Before contingency
- $1,340,000 – $1,770,000
2 × 200 m² · Premium · Moderate slope (CDC pathway assumed)
$1,510,000 – $2,095,000
All-in, before land, with a 10–15% contingency
- Construction
- $1,200,000 – $1,520,000
- Before contingency
- $1,370,000 – $1,820,000
2 × 200 m² · Premium · Steep slope (DA pathway assumed)
$1,565,000 – $2,185,000
All-in, before land, with a 10–15% contingency
- Construction
- $1,200,000 – $1,520,000
- Before contingency
- $1,425,000 – $1,900,000
Indicative only, not a quote. Includes site works, a geotechnical report, design and professional fees, approvals, council contributions, the Housing and Productivity Contribution, water and sewer connections, the Long Service Levy and landscaping. Excludes land, demolition, asbestos removal, subdivision registration, stamp duty and finance costs. In Greater Sydney the state contribution is about $4,500 higher.
What does a duplex cost per square metre?
Finish level sets most of the rate. CKS Projects usually recommends a mid-range specification: quality that holds its value, without spending on features that don't pay you back.
| Finish level | What you get | Per m² | 2 × 150 m² |
|---|---|---|---|
| Basic | Laminate benchtops, carpet, standard fixtures | $2,000–$2,400 | $600,000–$720,000 |
| Mid-range | Stone benchtops, hybrid floors, quality fixtures | $2,400–$2,800 | $720,000–$840,000 |
| Premium | High-end finishes throughout | $3,000–$3,800 | $900,000–$1,140,000 |
Single storey vs two storey
Single-storey duplex
The cheapest per square metre, but it needs a wider, larger block to fit the same floor area.
Two-storey duplex
The extra structure, stairs and trade coordination add cost, but more home fits on a smaller block.
Complex shapes, multiple roof lines and extensive glazing add 15–25% to construction. Every corner, roof valley and level change has a price.
A full duplex budget, line by line
The builder's construction price is not your final spend. Here is a complete budget for two 150 m² single-storey homes at a mid-range finish, on a flat Illawarra block, approved as complying development (CDC).
| Item | Low | High |
|---|---|---|
| Construction: 300 m² at $2,400–$2,800 per m² (mid-range) | $720,000 | $840,000 |
| Site preparation, flat block | $10,000 | $20,000 |
| Geotechnical report | $1,500 | $2,500 |
| Design and professional fees: architect, engineers, certifier, surveyor | $40,000 | $75,000 |
| Approval: CDC plus occupation certificate | $4,500 | $7,500 |
| Council development contributions (s7.11 / s7.12) | $15,000 | $35,000 |
| Housing and Productivity Contribution, Illawarra-Shoalhaven, 1 net new dwelling | $6,761 | $6,761 |
| Water and sewer connections, two dwellings | $20,000 | $30,000 |
| Long Service Levy, 0.25% of construction | $1,800 | $2,100 |
| Landscaping, driveways and fencing | $40,000 | $70,000 |
| Subtotal | $860,000 | $1,090,000 |
| Contingency, 10% (low) to 15% (high) | $85,000 | $160,000 |
| All-in, before land | $945,000 | $1,250,000 |
Before contingency, everything on top of construction adds about $140,000–$250,000 here, or roughly 19–30% of the build price. A sloping block, a DA or a premium specification pushes that higher.
The NSW charges most duplex quotes leave out
These are set by the NSW Government, your council or the water authority, not by the builder. Budget for them from day one.
Housing and Productivity Contribution
A state charge in Greater Sydney, the Illawarra-Shoalhaven, the Central Coast and the Lower Hunter. For a duplex on an existing lot, the existing lot is deducted, so you pay for one net new dwelling: $6,761.42 in the Illawarra-Shoalhaven or $11,269.04 in Greater Sydney (as at 1 October 2026, indexed quarterly).
Council development contributions
Councils levy these under section 7.11 (per dwelling) or section 7.12 (a percentage of cost, usually up to 1% of work over $200,000). A council needs an IPART review before it can charge more than $20,000 per dwelling under s7.11, or $30,000 in greenfield areas.
Long Service Levy
0.25% of the cost of building work of $250,000 or more, GST included. It must be paid before your CDC or construction certificate is released. On an $800,000 build it is $2,000.
Water, sewer and Section 73
Each dwelling needs its own connections. In Sydney Water's area, which covers Sydney and the Illawarra, a duplex or two-lot subdivision needs a Section 73 compliance certificate. The application costs $1,202.92, and any required works are quoted on top.
BASIX
Every new dwelling in NSW needs a BASIX certificate for energy, water and thermal performance. The commitments you make, such as glazing, insulation and water tanks, flow into the build cost.
Home building compensation cover
Your builder must take out home building compensation (HBC) cover for residential work over $20,000. NSW also gives you statutory warranties: 6 years for major defects and 2 years for other defects.
Sources: NSW Planning, Housing and Productivity Contribution; IPART, local infrastructure contributions; NSW Government, Long Service Levy; Sydney Water, Section 73; NSW Planning Portal, BASIX; SIRA, HBC; NSW Government, building contracts.
Site costs: slope, rock, soil and access
The ground under your duplex can move the budget more than any kitchen choice. A geotechnical report costs $1,500–$2,500, and it is the cheapest insurance you will buy.
- Flat block: $10,000–$20,000 for levelling and service trenches.
- Moderate slope: $40,000–$70,000 for cut and fill, retaining walls and drainage.
- Steep or escarpment block: $80,000–$120,000 for earthworks, multiple retaining walls and complex drainage.
- Rock: $150–$250 per cubic metre to remove. Severe rock adds $30,000–$60,000.
- Reactive clay: deeper footings cost $20,000–$40,000 more than a standard slab.
- High water table near the coast: drainage and damp-proofing add $15,000–$25,000.
- Tight access: narrow streets and difficult deliveries add 5–10% to labour.
- Knockdown sites: demolition and any asbestos removal are priced after inspection. More than 10 m² of non-friable asbestos needs a licensed removalist (SafeWork NSW).
Building on a slope? See sloping block builders in Wollongong. Replacing an old house? See knockdown rebuild in Wollongong.

Sydney vs Illawarra vs regional NSW: what changes?
Floor area, finish and site conditions drive the build price wherever you are. Location changes the charges and the trade costs around it.
| Cost item | Greater Sydney | Illawarra-Shoalhaven | Other regional NSW |
|---|---|---|---|
| Housing and Productivity Contribution (1 net new dwelling) | $11,269.04 | $6,761.42 | $6,761.42 in the Central Coast and Lower Hunter; not charged elsewhere |
| Council contributions | Set by each council's contributions plan. Check your council before you buy or design. | ||
| Water and sewer | Sydney Water: a Section 73 certificate is needed for subdivision | Your local water utility | |
| Trades and access | Illawarra labour rates sit below Sydney's and above rural NSW. Coastal sites with difficult access cost 10–15% more to build. | ||
Within the Illawarra, the northern suburbs such as Thirroul and Austinmer command premium prices for land and trades. Southern areas such as Albion Park and Shellharbour are usually more affordable to build in.
CDC vs DA: what each costs and how long it takes
| Complying development (CDC) | Development application (DA) | |
|---|---|---|
| When it applies | The duplex meets every standard of the Low Rise Housing Diversity Code, up to two storeys | Slope, vegetation, heritage or a non-standard design |
| Approval fees | $3,000–$5,000 | $8,000–$15,000, plus a construction certificate at $3,000–$5,000 |
| Extra reports | Usually fewer | $5,000–$15,000: traffic, acoustic, arborist and others as required |
| Time | In as little as 20 days | 12–16 weeks minimum |
| Both pathways | An occupation certificate ($1,500–$2,500), a BASIX certificate for each dwelling, and the Long Service Levy before work starts | |
Standards and CDC timing: Low Rise Housing Diversity Code and Low and Mid-Rise Housing Policy. Fee ranges are CKS Projects' guide figures. Read more on council approval.
How to bring the cost down without cutting corners
Keep the form simple
Simpler forms built well beat complex designs built cheaply. Fewer corners, roof valleys and level changes mean fewer hours on site.
Adapt a proven design to your block
Modifying a standard duplex design instead of starting from a blank page can save $10,000–$20,000 in design fees.
Spend on the right finishes
Budget fixtures save $15,000–$20,000 per dwelling but wear out sooner. Premium fixtures add $25,000–$35,000 per dwelling. Mid-range is usually the sweet spot.
Choose materials that perform
Locally available bricks cost less than imported stone. Porcelain tiles that look like marble cost about half as much and perform as well.
Take the CDC route where you can
If your block and design meet the code, a CDC means lower fees, fewer reports and an approval in weeks, not months.
Test the ground first
A $1,500–$2,500 geotechnical report up front prevents foundation surprises that can cost $50,000 or more.
How CKS Projects prices a duplex
Free duplex site assessment
We check lot size, frontage, zoning, slope and access before you spend anything on design.
Design and a complete budget
Construction, site works, fees and every council and state charge, set out up front.
Fixed-price contract
Your build is quoted at a fixed price for your block before you sign.
Build and handover
Around 9–14 months from design to completion, managed by one team.
More on duplex builders in Wollongong and dual occupancy builders. Weighing up the numbers as an investor? Read are duplexes a good investment in Wollongong? Building one home instead? See what a new house costs to build in NSW, or compare the cost of a granny flat behind your existing home.
Duplex cost FAQs
How much does it cost to build a duplex in NSW?
Construction alone typically costs $2,000–$3,800 per square metre, depending mostly on the finish level. Two 150 m² homes at a mid-range finish cost about $720,000–$840,000 to build. With site works, professional fees, council and state charges, connections, landscaping and a 10–15% contingency, the same duplex comes to about $945,000–$1.25 million, before the cost of the land.
How much does it cost to build a duplex in Sydney?
The building work is priced on the same drivers: floor area, finish level, storeys and site conditions. The state charge is higher in Greater Sydney. The Housing and Productivity Contribution is $11,269.04 per new dwelling there, compared with $6,761.42 in the Illawarra-Shoalhaven (rates as at 1 October 2026). Council contributions also vary by council. CKS Projects builds from Stanwell Park to Huskisson and inland to the Southern Highlands.
What is the cost per square metre to build a duplex?
CKS Projects' guide ranges are $2,000–$2,400 per m² for a basic finish, $2,400–$2,800 for mid-range (stone benchtops, hybrid floors, quality fixtures) and $3,000–$3,800 for premium. By storeys, single-storey duplexes run about $2,200–$2,600 per m² and two-storey duplexes about $2,600–$3,200 per m².
Is a single-storey duplex cheaper to build than a two-storey duplex?
Per square metre, yes. Single-storey runs about $2,200–$2,600 per m². Two-storey runs about $2,600–$3,200 per m², because of the extra structure and trade coordination. A two-storey design can fit more floor area on a smaller block, so compare total cost against the floor area each design gives you.
What does a builder's duplex quote usually leave out?
Most construction quotes leave out site preparation, the geotechnical report, design and engineering fees, approval fees, council contributions, the Housing and Productivity Contribution, water and sewer connections, the Long Service Levy and landscaping. In the worked example these add about $140,000–$250,000 on top of construction, before contingency. CKS Projects sets out the complete budget up front and quotes the build at a fixed price before you sign.
What council and government fees do you pay to build a duplex in NSW?
Expect approval fees, which are about $3,000–$5,000 for a CDC or $8,000–$15,000 for a DA. Then council development contributions under section 7.11 or 7.12, and the Housing and Productivity Contribution in Greater Sydney, the Illawarra-Shoalhaven, the Central Coast and the Lower Hunter. The Long Service Levy is 0.25% of the cost of work of $250,000 or more, paid before work starts. You also need a BASIX certificate. If you subdivide in Sydney Water's area, you need a Section 73 certificate, and the application costs $1,202.92.
How much extra does a sloping block add to a duplex?
On CKS Projects' figures, a flat block needs about $10,000–$20,000 of site works. A moderate slope needs $40,000–$70,000 for cut and fill, retaining walls and drainage. A steep escarpment block can add $80,000–$120,000. Rock costs about $150–$250 per cubic metre to remove, and severe rock can add $30,000–$60,000.
How much does a knockdown rebuild duplex cost?
The build costs the same as on a vacant block, plus demolition and any asbestos removal, which are priced after an inspection. In NSW, removing more than 10 m² of non-friable asbestos needs a licensed removalist. Because the Housing and Productivity Contribution deducts the existing lot, a knockdown duplex pays it for one net new dwelling.
How much contingency should I allow when building a duplex?
Allow 10–15% on top of your final estimate. Every duplex project runs into something unplanned: variations, ground conditions or price movements. Plan on 10% as a minimum and 15% to be safer.
Can I get a fixed price for building a duplex?
Yes. CKS Projects quotes the build at a fixed price for your block before you sign. It starts with a free duplex site assessment that checks lot size, frontage, zoning, slope and access before you spend anything on design.
How long does it take to build a duplex?
CKS Projects quotes around 9–14 months from design to completion. A complying development certificate (CDC) can be approved in as little as 20 days when every standard is met. A DA usually takes at least 12–16 weeks.
Get a real number for your block
Tell us your address and what you want to build. We'll check the block for free, then quote your duplex at a fixed price before you sign.
