Fixed Price vs Cost Plus Contracts: Which Should You Sign in NSW?

The short answer

Fixed price or cost plus: which should you sign?

A fixed price contract sets the total price for a defined scope before work starts, so the builder carries the risk of costs rising. A cost plus contract has no guaranteed final price: you pay the builder's actual costs plus a fee or margin, so you carry that risk. For a new home with complete plans, selections and a soil report, a fixed price gives you the most certainty.

  • Fixed pricethe builder carries the cost risk
  • Cost plusyou carry the cost risk
  • 10%maximum deposit in NSW
  • 10–15%contingency to hold back either way

A detailed fixed-price quote before you sign, with preliminaries itemised. NSW contractor licence 258735C.

By Keiron Moore, Director of CKS Projects, with 25+ years building on the South Coast. Updated October 2026.

Important Disclaimer:

“This article is general guidance, not an exact price guide, guaranteed returns, or a substitute for professional advice or a formal quote. Construction costs, rental yields, and capital growth examples reflect 2025 conditions and will vary with site constraints, design, materials, and market movements. Speak with a qualified financial adviser before making investment decisions. For accurate estimates and design recommendations for your site, contact CKS Projects. We’ll provide a comprehensive consultation and a formal quote tailored to your Wollongong build.”

Government charges are as published at the date shown and change over time.

Side by side

Fixed price vs cost plus at a glance

Fixed priceCost plus
The priceAgreed before work starts, for a defined scopeNot known until the work is finished
Who carries the risk of costs risingThe builder, except for approved variations and allowancesYou
What you payThe contract price, plus approved variations and any allowance adjustmentsVerified costs of labour and materials, plus the builder's fee or margin
How you payProgress payments at agreed stages, matched to the work donePayments as costs are incurred, supported by receipts or other verifying documents
SuitsNew homes with complete drawings, selections and a soil reportWork whose nature stops the final cost being calculated in advance
Watch forLarge provisional sums and prime cost allowancesNo ceiling on the final price; how the margin is calculated
A CKS Projects team member meeting clients inside the timber frame at Wombarra during construction
On site at Wombarra with CKS Projects. On a fixed price, changes made during the build are priced and agreed as variations.
Your protections

The NSW rules that protect you, whichever contract you sign

Written contract

Work over $5,000 including GST needs a written contract: a small-job contract up to $20,000 and a large-job contract above it.

Price on the first page

For work over $20,000 the contract price must be shown prominently on the first page, or the contract must carry a warning and an explanation if the price isn't known or may change.

Deposit capped at 10%

The maximum deposit you can be asked to pay is 10% of the contract price.

Insurance before any payment

On contracts over $20,000 the builder must give you a home building compensation certificate before asking for a deposit or any other payment.

Progress payments match the work

Contracts over $20,000 need a progress payment schedule. Payments must match the work carried out, and cost plus claims must be backed by receipts or other verifying documents.

No surprise price rises

On contracts over $20,000 the builder can't increase the price unless the contract contains a clause allowing it.

Sources: NSW Government, contracts for building work; NSW Fair Trading, guide to home building contracts; NSW Fair Trading, contract checklist.

Read the fine print

What can still change on a fixed price contract

A fixed price is only as fixed as the scope and allowances behind it. Three things can move it after you sign:

  1. Variations

    Changes to the agreed work, whether you ask for them or site conditions require them. Each one should be documented and priced before the work proceeds.

  2. Provisional sums

    Allowances for work that can't be priced yet. On CKS Projects' figures, rock costs $150–$250 per cubic metre to remove and severe rock can add $30,000–$60,000, which is why a soil report before you sign matters.

  3. Prime cost items

    Allowances for items you haven't chosen. If the contract allows $18,000 for a kitchen and you choose one that costs $24,000, you pay the difference.

This is why two quotes for the same home can be far apart. In one CKS Projects example, an $850,000 quote needed another $65,000 to actually complete the project, once the items it left out were added. Compare quotes on what they include, not the headline number. Read more on fixed price quotes vs estimates.

The other option

When cost plus makes sense

NSW Fair Trading describes cost plus as a contract with no guaranteed final cost, often used where the nature of the project prevents the final cost from being calculated. The owner pays the builder's verified costs and fees at regular intervals.

If you do sign a cost plus contract:

  • get the builder's estimate of the total cost in writing, and ask how often you'll get cost reports;
  • make sure the contract explains exactly how the fee or margin is calculated;
  • check every progress claim against its receipts or invoices;
  • hold back a larger contingency than the 10–15% you would on a fixed price, because there is no ceiling.
Before you sign

Questions to ask before you sign any building contract

  1. Is the contract price on the first page, or is there a warning that it isn't known or may change?
  2. Which items are provisional sums or prime cost items, and how big are those allowances?
  3. Are the preliminaries itemised: site setup, scaffolding, fencing, supervision, connections, the Long Service Levy and insurance?
  4. Has a geotechnical report been done, and are the footings priced on it?
  5. How are variations priced and approved before the work goes ahead?
  6. Is the deposit 10% or less, and have I received the home building compensation certificate?
  7. Does the progress payment schedule match the stages of work?
Working with CKS Projects

How CKS Projects prices a build

Wombarra Clifftops, built by CKS Projects on a fixed-price contract.
  1. Free discovery call

    Talk through your land, ideas and budget with the builder, not a salesperson.

  2. Design and selections

    Your home is designed for your block, and finishes are chosen with specialist support before pricing.

  3. Itemised preliminaries

    Site setup, management, compliance and logistics costs are identified and priced before a contract is issued.

  4. Fixed-price contract

    You receive a detailed fixed-price quote before signing. Any variation is documented and priced before work proceeds.

Working out a budget first? See what a house costs to build in NSW and why a paid estimate is worth it. Ready to build? See custom home builders in Wollongong, new home building or a knockdown rebuild on your own land. Keeping the price down? Read the cheapest way to build a house in NSW.

Questions

Building contract FAQs

What is the difference between a fixed price and a cost plus contract?

Under a fixed price contract the builder agrees a total price for a defined scope of work, and the price changes only through agreed variations or the allowances written into the contract. Under a cost plus contract there is no guaranteed final price: you pay the builder's verified costs plus a fee or margin as the work is done.

Are cost plus contracts legal in NSW?

Yes. For work over $20,000 the contract must show the contract price prominently on the first page, or carry a warning and an explanation if the price is not known or may change. Progress payments under a cost plus contract must be supported by receipts or other verifying documents.

Is a fixed price contract really fixed?

The agreed scope is. The price can still move through variations you approve, and through provisional sums and prime cost items, which are allowances for work or items that weren't fully priced when you signed. The fewer allowances a contract carries, the more fixed the price really is.

Which is cheaper, fixed price or cost plus?

Neither is cheaper by default. A fixed price builds the builder's risk into the price, so you know your number up front. Cost plus passes the risk to you: it can come in lower if nothing goes wrong, and there is no ceiling if something does.

What is a provisional sum in a building contract?

An allowance for work the builder can't price exactly yet, such as rock excavation before the ground is opened up. If the work costs more than the allowance, you pay the difference, and the contract may add the builder's margin to it.

What is a prime cost item?

An allowance for an item you haven't chosen yet, such as appliances, tapware or a kitchen. If the kitchen allowance is $18,000 and the kitchen you choose costs $24,000, you pay the difference.

How much deposit can a builder ask for in NSW?

No more than 10% of the contract price. On contracts over $20,000 the builder must also give you a home building compensation certificate before asking for any deposit or payment.

When does a cost plus contract make sense?

When the nature of the work stops the final cost being calculated in advance, so the scope can't be defined well enough to fix a price. For a new home with complete drawings, selections and a soil report, a fixed price is usually achievable.

How do I keep variations down on a fixed price contract?

Finish your selections before you sign, get a geotechnical report ($1,500–$2,500) so the footings are priced on real ground conditions, and ask for preliminaries and allowances to be itemised. Then budget a 10–15% contingency for changes you choose to make.

Does CKS Projects build on a fixed price?

Yes. CKS Projects gives you a detailed fixed-price quote before any contract is signed, with preliminary costs itemised. Any variation is documented and priced before work proceeds.

About the author

Keiron Moore is the Director of CKS Projects, a Wollongong builder based in Unanderra with 25+ years' experience in residential construction. CKS Projects holds NSW contractor licence 258735C and won at the 2026 MBA NSW Southern Regions awards for Wombarra Clifftops. See our verified credentials.

Get a fixed price for your build

Tell us about your land and what you want to build. We'll talk it through for free, then give you a detailed fixed-price quote before you sign anything.

Previous
Previous

Spec Home vs Project Home vs Custom Home: Which Is Right for You?

Next
Next

How Much Does It Cost to Build a 4 Bedroom House in NSW? (2026 Guide)