How Much Does a Knockdown Rebuild Cost in NSW? (2026 Guide)

The short answer

What a knockdown rebuild costs in NSW

The new home typically costs $2,000–$3,800 per square metre to build, set mostly by the finish level, so a 240 m² home at a mid-range finish costs about $576,000–$672,000. Site works, fees, council and state charges, connections, landscaping and a 10–15% contingency take the same home to about $765,000–$1,020,000 all-in. Demolition and asbestos are priced after an inspection. You keep the land, so there is no land cost and no stamp duty.

  • $2,000–$3,800per m², construction only
  • $576k–$672kto build 240 m², mid-range
  • $765k–$1.02Mall-in, worked example
  • 10–15%contingency to hold back

Free site assessment with the builder. Demolition, approvals and build in one fixed-price contract. NSW contractor licence 258735C.

By Keiron Moore, Director of CKS Projects, with 25+ years building on the South Coast. Updated October 2026.

Important Disclaimer:

“This article is general guidance, not an exact price guide, guaranteed returns, or a substitute for professional advice or a formal quote. Construction costs, rental yields, and capital growth examples reflect 2025 conditions and will vary with site constraints, design, materials, and market movements. Speak with a qualified financial adviser before making investment decisions. For accurate estimates and design recommendations for your site, contact CKS Projects. We’ll provide a comprehensive consultation and a formal quote tailored to your Wollongong knockdown rebuild.”

Government charges are as published at the date shown and change over time.

Knockdown rebuild cost estimator

Estimate your rebuild in three clicks

Choose the size of the new home, the finish and your block. The range uses CKS Projects' guide figures and Wollongong's current council and state charges.

1. Size of the new home
2. Finish level
3. Your block

180 m² · Basic · Flat (CDC pathway assumed)

$525,000 – $740,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$360,000 – $432,000
Before contingency
$475,000 – $640,000

180 m² · Basic · Moderate slope (CDC pathway assumed)

$560,000 – $795,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$360,000 – $432,000
Before contingency
$505,000 – $690,000

180 m² · Basic · Steep slope (DA pathway assumed)

$615,000 – $890,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$360,000 – $432,000
Before contingency
$560,000 – $770,000

180 m² · Mid-range · Flat (CDC pathway assumed)

$605,000 – $825,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$432,000 – $504,000
Before contingency
$550,000 – $715,000

180 m² · Mid-range · Moderate slope (CDC pathway assumed)

$635,000 – $880,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$432,000 – $504,000
Before contingency
$580,000 – $765,000

180 m² · Mid-range · Steep slope (DA pathway assumed)

$695,000 – $970,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$432,000 – $504,000
Before contingency
$630,000 – $845,000

180 m² · Premium · Flat (CDC pathway assumed)

$725,000 – $1,030,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$540,000 – $684,000
Before contingency
$655,000 – $900,000

180 m² · Premium · Moderate slope (CDC pathway assumed)

$755,000 – $1,090,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$540,000 – $684,000
Before contingency
$685,000 – $950,000

180 m² · Premium · Steep slope (DA pathway assumed)

$815,000 – $1,180,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$540,000 – $684,000
Before contingency
$740,000 – $1,030,000

240 m² · Basic · Flat (CDC pathway assumed)

$655,000 – $905,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$480,000 – $576,000
Before contingency
$595,000 – $790,000

240 m² · Basic · Moderate slope (CDC pathway assumed)

$690,000 – $965,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$480,000 – $576,000
Before contingency
$625,000 – $840,000

240 m² · Basic · Steep slope (DA pathway assumed)

$750,000 – $1,055,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$480,000 – $576,000
Before contingency
$680,000 – $920,000

240 m² · Mid-range · Flat (CDC pathway assumed)

$765,000 – $1,020,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$576,000 – $672,000
Before contingency
$695,000 – $885,000

240 m² · Mid-range · Moderate slope (CDC pathway assumed)

$795,000 – $1,075,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$576,000 – $672,000
Before contingency
$725,000 – $935,000

240 m² · Mid-range · Steep slope (DA pathway assumed)

$855,000 – $1,170,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$576,000 – $672,000
Before contingency
$775,000 – $1,015,000

240 m² · Premium · Flat (CDC pathway assumed)

$920,000 – $1,300,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$720,000 – $912,000
Before contingency
$840,000 – $1,130,000

240 m² · Premium · Moderate slope (CDC pathway assumed)

$955,000 – $1,355,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$720,000 – $912,000
Before contingency
$870,000 – $1,180,000

240 m² · Premium · Steep slope (DA pathway assumed)

$1,015,000 – $1,445,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$720,000 – $912,000
Before contingency
$920,000 – $1,260,000

300 m² · Basic · Flat (CDC pathway assumed)

$790,000 – $1,075,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$600,000 – $720,000
Before contingency
$720,000 – $935,000

300 m² · Basic · Moderate slope (CDC pathway assumed)

$820,000 – $1,130,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$600,000 – $720,000
Before contingency
$750,000 – $985,000

300 m² · Basic · Steep slope (DA pathway assumed)

$880,000 – $1,225,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$600,000 – $720,000
Before contingency
$800,000 – $1,065,000

300 m² · Mid-range · Flat (CDC pathway assumed)

$920,000 – $1,215,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$720,000 – $840,000
Before contingency
$840,000 – $1,055,000

300 m² · Mid-range · Moderate slope (CDC pathway assumed)

$955,000 – $1,270,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$720,000 – $840,000
Before contingency
$870,000 – $1,105,000

300 m² · Mid-range · Steep slope (DA pathway assumed)

$1,015,000 – $1,365,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$720,000 – $840,000
Before contingency
$920,000 – $1,185,000

300 m² · Premium · Flat (CDC pathway assumed)

$1,120,000 – $1,565,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$900,000 – $1,140,000
Before contingency
$1,020,000 – $1,360,000

300 m² · Premium · Moderate slope (CDC pathway assumed)

$1,155,000 – $1,620,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$900,000 – $1,140,000
Before contingency
$1,050,000 – $1,410,000

300 m² · Premium · Steep slope (DA pathway assumed)

$1,210,000 – $1,715,000

All-in, with a 10–15% contingency. You already own the land.

Construction
$900,000 – $1,140,000
Before contingency
$1,100,000 – $1,490,000

Indicative only, not a quote. Includes site works, a geotechnical report, design and professional fees, approvals, Wollongong's s7.12 contribution (nil to 1%), water and sewer connections, the Long Service Levy and landscaping. Excludes demolition and asbestos removal (priced after inspection), temporary accommodation, removalists and finance costs.

Before the new slab

What a rebuild costs that a vacant block doesn't

Building on land you already own saves the land and the duty. In return, the old house has to come off the block safely and legally first.

  • Demolition: priced after an inspection. A single-storey fibro house is a different job from a two-storey brick home with a pool. It covers licensed demolition, waste disposal and site clean-up.
  • Asbestos: a qualified inspector assesses the house first, so removal becomes a defined cost rather than an open one. A licensed removalist must remove any friable asbestos and any bonded asbestos over 10 square metres. Demolition proceeds only after a clearance certificate.
  • Services: power, water, sewer and gas are disconnected before demolition and reconnected for the new home. These take time to book, so they are scheduled early.
  • Somewhere to live: once demolition starts the site is not habitable until handover. Budget rent, removalists and storage for the build period.
  • No stamp duty: no property changes hands, so no transfer duty applies. You still pay council rates on the land.

Asbestos rules: SafeWork NSW. Paying for it: knockdown rebuild finance options.

Excavator demolishing an old weatherboard house before a knockdown rebuild
Demolition comes after the asbestos clearance certificate and the service disconnections.
Construction rates

What does the new home cost per square metre?

Once the block is clear, the new home is priced like any other build. The finish level sets most of the rate.

Finish levelWhat you getPer m²240 m² home
BasicLaminate benchtops, carpet, standard fixtures$2,000–$2,400$480,000–$576,000
Mid-rangeStone benchtops, hybrid floors, quality fixtures$2,400–$2,800$576,000–$672,000
PremiumHigh-end finishes throughout$3,000–$3,800$720,000–$912,000
Construction only. CKS Projects guide ranges for 2025–26.

Complex shapes, multiple roof lines and extensive glazing add 15–25% to construction. Every corner, roof valley and level change has a price.

Worked example

A full knockdown rebuild budget, line by line

Here is a complete budget for replacing a single-storey brick house with a 240 m² single home at a mid-range finish, on a flat block in Wollongong, approved as complying development (CDC).

ItemLowHigh
Construction: 240 m² at $2,400–$2,800 per m² (mid-range)$576,000$672,000
Site preparation, flat block$10,000$20,000
Geotechnical report$1,500$2,500
Design and professional fees: architect, engineers, certifier, surveyor$40,000$75,000
Approval: CDC for demolition and the new home, plus occupation certificate$4,500$7,500
Council contribution, Wollongong s7.12 (nil if exempt, otherwise 1%)$0$6,720
Water and sewer connections$20,000$30,000
Long Service Levy, 0.25% of construction$1,440$1,680
Landscaping, driveways and fencing$40,000$70,000
Subtotal$695,000$885,000
Contingency, 10% (low) to 15% (high)$70,000$135,000
All-in (you already own the land)$765,000$1,020,000
Totals rounded to the nearest $5,000. Not included: demolition and asbestos removal (priced after inspection), temporary accommodation, removalists and storage, and finance costs.
State and council charges

The council and NSW charges on a knockdown rebuild

These are set by the NSW Government or your council, not by the builder. Budget for them from day one.

Council contributions

Wollongong's City-Wide Development Contributions Plan (in force from 31 August 2026) levies nil up to $100,000, 0.5% from $100,000 to $200,000 and 1% above $200,000 of the cost of development. It cannot be levied on a single dwelling where a s7.11 contribution was paid at subdivision and demand does not increase, so many one-for-one rebuilds pay nothing. Ask council for an estimate. Other councils have their own plans.

Long Service Levy

0.25% of the cost of building work of $250,000 or more, GST included. It must be paid before your CDC or construction certificate is released. On a $650,000 build it is $1,625.

Housing and Productivity Contribution

Charged on residential subdivision and medium- and high-density housing in the Illawarra-Shoalhaven and other HPC regions. The rate tables do not list a single dwelling house. Knock down and build a duplex, and it applies to one net new dwelling: $6,761.42 in the Illawarra-Shoalhaven (1 October 2026, indexed quarterly).

BASIX

Every new home in NSW needs a BASIX certificate for energy, water and thermal performance. The commitments you make, such as glazing, insulation and water tanks, flow into the build cost.

Asbestos removal

Regulated work. A Class A licensed removalist must remove friable asbestos, and more than 10 square metres of bonded (non-friable) asbestos needs a Class B or Class A licensed removalist. Waste goes to a licensed facility.

Home building compensation cover

Your builder must take out home building compensation (HBC) cover for residential work over $20,000. A rebuild is a new home, so the statutory warranties cover the whole house: 6 years for major defects and 2 years for other defects.

Sources: Wollongong City Council, City-Wide Development Contributions Plan; NSW Government, Long Service Levy; NSW Planning, Housing and Productivity Contribution; NSW Planning Portal, BASIX; SafeWork NSW, asbestos; SIRA, HBC.

Below the slab

Site costs: slope, rock, soil and access

The old house may have sat on a flat pad, but the new one is engineered for the block as it really is. A geotechnical report costs $1,500–$2,500, and it is the cheapest insurance you will buy.

  • Flat block: $10,000–$20,000 for levelling and service trenches.
  • Moderate slope: $40,000–$70,000 for cut and fill, retaining walls and drainage.
  • Steep or escarpment block: $80,000–$120,000 for earthworks, multiple retaining walls and complex drainage.
  • Rock: $150–$250 per cubic metre to remove. Severe rock adds $30,000–$60,000.
  • Reactive clay: deeper footings cost $20,000–$40,000 more than a standard slab.
  • High water table near the coast: drainage and damp-proofing add $15,000–$25,000.
  • Tight access: narrow streets, a narrow frontage or a steep driveway affect machinery for demolition and deliveries, adding 5–10% to labour.

Rebuilding on a slope? See sloping block builders in Wollongong.

Wombarra Clifftops: a split-level rebuild on a clifftop slip area.
Your options

Rebuild vs renovate vs sell and buy: where the money goes

Knockdown rebuildMajor renovationSell and buy again
LandYou keep itYou keep itYou buy again in the same market
Stamp dutyNoneNoneTransfer duty on the purchase
Extra costsDemolition, asbestos, temporary accommodationWhatever is found behind the wallsAgent fees, moving twice
Cost certaintyPriced from a survey, a geotechnical report and a full designHidden problems often surface after work startsPrice set by the market
What you end up withA new home designed for your block, warranties on the whole houseAn old house with new partsSomeone else's design, possibly a different street

Renovating usually wins when the structure is sound and the layout is close to what you want, or the house has character a rebuild would lose. Read more on why people choose to knock down and rebuild. Thinking of two homes on the block? See the NSW duplex cost guide.

Approvals

CDC vs DA: what each costs and how long it takes

You need approval for both the demolition and the new home, and they are usually lodged together.

Complying development (CDC)Development application (DA)
When it appliesThe demolition and the new home meet the set state standardsSlope, heritage, bushfire, flooding or a non-standard design
Approval fees$3,000–$5,000$8,000–$15,000, plus a construction certificate at $3,000–$5,000
Extra reportsUsually fewer$5,000–$15,000, as required
TimeIn as little as 20 daysCommonly months in the Illawarra
Both pathwaysAn occupation certificate ($1,500–$2,500), a BASIX certificate, and the Long Service Levy before work starts

CDC timing: NSW Planning, complying development. Fee ranges are CKS Projects' guide figures. Read more on council approval.

Working with CKS Projects

How CKS Projects prices a knockdown rebuild

Wombarra Clifftops: winner, Contract Homes $1.9M–$2M, 2026 MBA NSW Southern Regions Excellence in Building Awards.
  1. Free site assessment

    Keiron walks your block: slope, demolition access, soil, orientation and existing services.

  2. Design and a complete budget

    Demolition, asbestos, site works, fees and every council and state charge, set out up front.

  3. One fixed-price contract

    No provisional sums hiding unknowns. The only thing that changes the number is a variation you choose to make.

  4. Demolition, build and handover

    Most rebuilds take 6–12 months from design to handover, managed by one team.

Comparing builders? Ask each one whether the price is fixed or contains provisional sums, what is excluded, and who attends the site assessment. More on knockdown rebuild builders in Wollongong.

Questions

Knockdown rebuild cost FAQs

How much does a knockdown rebuild cost in NSW?

A knockdown rebuild costs the new home plus everything it takes to clear the block. Construction typically runs $2,000–$3,800 per square metre, set mostly by the finish level, so a 240 m² home at a mid-range finish costs about $576,000–$672,000 to build. Site works, professional fees, approvals, council and state charges, connections, landscaping and a 10–15% contingency take the same home to about $765,000–$1,020,000. Demolition and any asbestos removal are priced after an inspection. Because you already own the land, there is no land cost and no stamp duty.

How much does it cost to demolish a house in Wollongong?

Demolition is priced after an inspection, because it depends on the house: a single-storey fibro house is a different job from a two-storey brick home with a pool. The price also turns on any asbestos found, access for machinery and waste disposal. CKS Projects includes demolition in its fixed-price tender, so it is not a separate bill.

How much does asbestos removal add to a knockdown rebuild?

A qualified inspector assesses the house before demolition, and the report sets the scope, so removal becomes a defined cost rather than an open one. Under SafeWork NSW rules, a licensed removalist must remove any friable asbestos and any amount of bonded asbestos over 10 square metres.

What is the cost per square metre to build the new home?

CKS Projects' guide ranges are $2,000–$2,400 per m² for a basic finish, $2,400–$2,800 for mid-range (stone benchtops, hybrid floors, quality fixtures) and $3,000–$3,800 for premium. Complex shapes, multiple roof lines and extensive glazing add 15–25% to construction.

Is a knockdown rebuild cheaper than buying a new house?

Often it is, because you keep the land and pay no transfer duty. Selling and buying again means duty on the purchase, agent fees and moving twice, and you may not find the same location again. A rebuild means demolition, a construction budget and somewhere to live while you build. Compare the two on a full budget, not on the build price alone.

Is it cheaper to renovate or knock down and rebuild?

A renovation quote starts lower, but it cannot price what is behind the walls. On older fibro and brick-veneer houses, asbestos, old wiring, termite damage and footings that cannot carry a second storey often push a major renovation close to the cost of a rebuild, and you still end up with an old house underneath. A rebuild is priced from a survey, a geotechnical report and a full design, so the contract figure is known before work starts.

What council and government fees apply to a knockdown rebuild?

Expect approval fees for the demolition and the new home, which are usually lodged together: about $3,000–$5,000 for a CDC or $8,000–$15,000 for a DA. In Wollongong the city-wide contributions plan levies 1% of the cost of development over $200,000, but it cannot be levied on a single dwelling where a section 7.11 contribution was paid at subdivision and demand does not increase. The Long Service Levy is 0.25% of building work of $250,000 or more, paid before work starts. Every new home also needs a BASIX certificate.

Do I pay the Housing and Productivity Contribution on a knockdown rebuild?

The NSW rate tables charge it on residential subdivision and on medium- and high-density housing, and they do not list a single dwelling house. If you knock down and build a duplex instead, it applies to one net new dwelling, because the existing lot is deducted: $6,761.42 in the Illawarra-Shoalhaven as at 1 October 2026. Your certifier confirms the amount on the NSW Planning Portal.

What costs sit outside a knockdown rebuild contract?

Budget separately for temporary accommodation from demolition until handover, removalists and storage, council rates and insurance on the land during construction, and your lender's fees on a construction loan. A construction loan does not cover the period when you have no habitable house.

How much contingency should I allow for a knockdown rebuild?

Allow 10–15% on top of your final estimate for variations, ground conditions and price movements. On a fixed-price contract the build figure does not move unless you change the design, but the contingency still covers your own choices and the costs outside the contract.

How long does a knockdown rebuild take?

Most CKS Projects knockdown rebuilds take 6–12 months across design, documentation, approval, demolition and construction. A complying development certificate can be issued in as little as 20 days. A DA commonly takes months in the Illawarra.

About the author

Keiron Moore is the Director of CKS Projects, a Wollongong builder based in Unanderra with 25+ years' experience in residential construction. CKS Projects holds NSW contractor licence 258735C and won at the 2026 MBA NSW Southern Regions awards for Wombarra Clifftops, a knockdown rebuild. See our verified credentials.

Get a real number for your rebuild

Tell us your address and what you want to build. We'll check the block for free, then quote the demolition and your new home at one fixed price before you sign.


DESIGNING A DUPLEX THAT DELIVERS RETURNS

Whether you're looking to live in one and rent the other, build for extended family, or maximise your land’s potential, this guide will help you avoid costly mistakes and make confident decisions.

Previous
Previous

How Do You Get Accurate Building Quotes for Your Duplex in Wollongong?

Next
Next

Why Should You Consider a Corner Block for Your Duplex in Wollongong?